Client: Digital Realty Trust
General Contractor: TLM Group
Date: 2021-2023
Services
Colo 8 PDU Upgrade Phase I, II, III & IV. Back-feed & Demo Remote Power Panels, Demo Legacy Power Distribution Units & Static Switches, Installation of new Remote Power Panels & Power Distribution Units, Commissioning Support.
365 Main St.
San Francisco, CA
Biosolids Package 2 San Francisco, CA
SFMTA Parking Garages San Francisco, CA
Client: SFMTA
Date: 2023
Services
Installation of security cameras and horn systems at the SFMTA parking garages located at Ellis St. & O’Farrell St. and Polk St. & Bush St.
General Contractor: Cahill Contractors
Date: 2022 - 2023
Services
Full solar system installation at 105 Units-Maceo May Apartments.
Photo Credit: www.mithun.com
40 Avenue of the Palms
Treasure Island, San Francisco, CA
General Contractor: Cahill Contractors
Date: 2023
Services
Full Solar System Installation
Photo Credit: www.cahill-sf.com
Mission Bay South Block 9
Treasure Island, San Francisco, CA
General Contractor: Suffolk
Date: 2022
Services
(3) Full Solar System Installations of 3 Buildings A, B & D.
Photo Credit: www. businesswire.com
1629 Market St.
San Francisco, CA
General Contractor: Plant Construction
Client: Port of San Francisco
Date: 2021
Services
Installation of 4” Rigid Conduits from Vault in Street to 12KV Switchgear.
Port of San Francisco – Pier 70
San Francisco, CA
Client: Sunbelt
Date: 2020-2021
Services
Installation of new BMS Systems at a New Ground Up 2-Story Data Center (30,000 sq.ft.)
1550 Space Park
Santa Clara, CA
365 Main St.
San Francisco, CA
Client: Digital Realty
General Contractor: TLM Group
Date: 2020
Services
Client: Cupertino Electric
General Contractor: Pankow
Date: 2020
Services
Full Solar Panel System Installation & Supervision of AV System Installation at New Ground Up High-Rise for the SF Department of Public Works HQ.
49 South Van Ness
San Francisco, CA
Client: Prime Data Centers
Date: 2019
Services
Generator Inspection and Testing. Lock Out/Tag Out and shut down (2) 2-MegaWatt generators; conducted termination and torque inspection; energized, tested, and conducted IR scan.
Prime Data Centers
Sacramento, CA
Client: Digital Realty
General Contractor: Northshore
Date: 2019
Services
Removal and replacement of 13 CRAC units, upgraded the power and fire alarm system, and provided electrical and fire alarm design, along with stamped drawings.
Digital Realty - Colo-8 CRAC Replacement - San Francisco
General Contractor: MIK Construction
Date: 2023
Services
Power, Lighting & Life Safety
SFMTA-Chinatown Station SFPD
San Francisco
General Contractor: City Building Inc.
Date: 2023
Services
Power, Lighting & Life Safety
SFMTA-Union Square Station SFPD Down Room & Kiosk
San Francisco
Colo-2 PDU Upgrade Phase-I & Phase-II - San Francisco
Client: Digital Realty
General Contractor: TLM Group
Date: 2021-2023
Services
Backfeed & Demo Remote Power Panels, Demo Legacy Power Distribution Units & Static Switches, Installation of new Remote Power Panels & Power Distribution Units, Commissioning Support
Client: Digital Realty
General Contractor: The CORE Group
Date: 2023 - 2024
Services
Removal and replacement of 13 CRAC units, upgraded the power and fire alarm system, and provided
electrical and fire alarm design, along with stamped drawings
Colo-2 CRAC Upgrade